Beta
BC:14015:en
BC:14015:en — Water Sustainability Act
Beta. Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Analyze this law with AIDefinitions
1
1
In this Act:
agricultural land reserve
has the same meaning as in the
Agricultural Land Commission Act
;
alter
, in relation to a well, means
a
undertake a structural change to a well related to the well's depth, diameter or screen assembly,
b
install a surface seal in a well that does not have one, or
c
hydrofracture a well to enhance groundwater supply from the well;
appeal board
means the Environmental Appeal Board continued under section 93 of the
Environmental Management Act
;
applicant
means a person applying for
a
an authorization, an amendment to an authorization, a transfer of the appurtenancy of an authorization or an apportionment of the rights under a licence,
b
a change approval, an amendment to a change approval or the transfer of the appurtenancy of a change approval,
c
a drilling authorization, an amendment to a drilling authorization or the transfer of the appurtenancy of a drilling authorization,
d
the transfer of an application for an authorization, or
e
the abandonment of all or some of the person's rights under an authorization;
aquatic ecosystem
, in relation to a stream, means the natural environment of the stream, including
a
the stream channel, the vegetation in the stream and the water in the stream, and
b
fish, wildlife and other living organisms insofar as their life processes
i
are carried out in the stream, and
ii
depend on the natural environment of the stream;
aquifer
means
a
a geological formation,
b
a group of geological formations, or
c
a part of one or more geological formations
that is groundwater bearing and capable of storing, transmitting and yielding groundwater;
authorization
, except in references to drilling authorization, means a licence or use approval;
beneficial use
,
a
in relation to a use of water under an authorization, means using the water
i
as efficiently as practicable,
ii
in accordance with any applicable regulations, and
iii
for the water use purposes, in the manner and in the period or at the times, authorized by the authorization, and
b
in relation to a use of water other than under an authorization, means using the water for a water use purpose
i
as efficiently as practicable,
ii
in accordance with any applicable regulations, and
iii
in accordance with the provisions of this Act or the regulations that apply in relation to the use of water without an authorization;
beneficial use declaration
means a declaration described in section 30 (2)
[beneficial use]
;
change approval
means an approval, to make changes in and about a stream, issued under section 11 (1)
[changes in and about a stream]
or a similar approval issued under a former Act;
changes in and about a stream
means
a
any modification to the nature of a stream, including any modification to the land, vegetation and natural environment of a stream or the flow of water in a stream, or
b
any activity or construction within a stream channel that has or may have an impact on a stream or a stream channel;
compliance agreement
means an agreement described in section 102 (1), (2) and (3)
[compliance agreements]
;
comptroller
means the person designated as the Comptroller of Water Rights under section 114 (1)
[administration]
;
conditional licence
means a licence, issued under this or a former Act, that authorizes the licensee to construct works, or divert and use water, before the issue of a final licence;
construct
, in relation to a well, means
a
drill the well,
b
alter the well,
c
develop the well,
d
repair or maintain the well,
e
inject water or any other substance into the well, or
f
construct, install, replace, repair, alter or remove works that relate to groundwater or the well;
critical environmental flow threshold
, in relation to the flow of water in a stream, means the volume of water flow below which significant or irreversible harm to the aquatic ecosystem of the stream is likely to occur;
Crown land
means land, whether or not it is covered by water, that is vested in the government;
date of first use
, in relation to a use of groundwater from an aquifer for a water use purpose, means the date from which the comptroller, a water manager or an engineer is satisfied in accordance with the regulations that groundwater from the aquifer has been used
a
regularly and beneficially on an ongoing basis,
b
for the water use purpose, and
c
on land, or for a mine or undertaking, to which, if the water use purpose were licensed, the licence would be appurtenant;
deactivate
, in relation to works, means take the works out of service temporarily;
debris
means
a
clay, silt, rock or similar material, or
b
any material, natural or otherwise, from construction or demolition;
decision maker
, in relation to a decision under this Act, means
a
the person authorized to make the decision, and
b
if more than one person is authorized to make that decision, the person who is making or has made that decision,
whether on application or on the person's own initiative;
decommission
, in relation to works, means take the works out of service permanently;
dedicated agricultural water
means water that is dedicated under section 82 (1)
[plan regulations — dedicated agricultural water]
for qualifying agricultural use on qualifying agricultural land;
development district
has the same meaning as "district" in section 58
[definitions]
of the
Drainage, Ditch and Dike Act
;
divert
means,
a
in relation to water in a stream, cause the water to leave the stream channel, whether to cause the water to flow into another stream channel or a reservoir or otherwise, and
b
in relation to water in an aquifer, cause the water to leave the aquifer,
and includes extract or impound water from a stream or an aquifer;
drill
, in relation to a well, means make the well by drilling, boring, driving, jetting or excavating;
drilling authorization
means an authorization issued under section 62
[drilling authorizations]
;
drinking water officer
has the same meaning as in section 1
[definitions]
of the
Drinking Water Protection Act
;
engineer
, except in the definition of "professional" in section 48
[definitions for Division 3 of Part 3]
, means a person designated as an engineer under section 114 (5)
[administration]
;
environmental flow needs
, in relation to a stream, means the volume and timing of water flow required for the proper functioning of the aquatic ecosystem of the stream;
farm use
, subject to the regulations, has the same meaning as in section 1 (1)
[definitions]
of the
Agricultural Land Commission Act
;
final licence
means a licence, issued under this or a former Act, that authorizes the diversion and use of water but does not authorize the construction of works;
former Act
means any Act containing provisions respecting the diversion and use of water that came into force before the date this definition comes into force;
geotechnical well
means a well, other than a monitoring well or a well that is used to divert groundwater, that is drilled for the purpose of obtaining geotechnical, hydrological, hydrochemical or stratigraphical information;
government corporation
has the same meaning as in section 1
[definitions]
of the
Financial Administration Act
;
government water record
means information, respecting the quality or quantity of water in a stream or aquifer, a person's use of water from a stream or aquifer, or works, that is in the records of
a
the minister,
b
the provincial health officer appointed under the
Public Health Act
,
c
a regional health board designated under the
Health Authorities Act
,
d
a prescribed minister, or
e
a prescribed government corporation;
groundwater
means water naturally occurring below the surface of the ground;
improvement district
means, as the context requires,
a
the corporation into which the residents of an area are incorporated as an improvement district under the
Local Government Act
or a former Act, or
b
the geographic area of the improvement district corporation;
licence
means a conditional licence or a final licence;
local trust committee
has the same meaning as in section 1
[definitions]
of the
Islands Trust Act
;
mine
includes a placer or mineral claim or land held or occupied for the purpose of winning a mineral from the claim or land, whether held in fee simple or by virtue of a record, registration, lease or licence;
mineral
means
a
an ore of metal or a natural substance capable of being mined
i
that is in the place or position in which the ore or substance was originally formed or deposited or is in talus rock, and includes
A
rock and other materials from mine tailings, dumps and previously mined deposits of minerals, and
B
dimension stone, or
ii
that is either loose, or found in fragmentary or broken rock that is not talus rock and occurs in loose earth, gravel and sand, and includes rock or other materials from placer mine tailings, dumps and previously mined deposits of placer minerals, or
b
coal,
but does not include petroleum or natural gas;
monitoring well
means a well that
a
is used or intended to be used for the purpose of monitoring, observing, testing, measuring or assessing
i
the level, quantity or quality of groundwater, or
ii
subsurface conditions, including geophysical conditions, and
b
is not used or intended to be used for the purpose of
i
exploring for or diverting groundwater for a water use purpose, or
ii
injecting water or any other substance into groundwater on an ongoing basis;
natural boundary
has the same meaning as in section 1
[definitions]
of the
Land Act
;
officer
means
a
a person designated as an officer under section 114 (6)
[administration]
of this Act, or
b
a conservation officer as defined in section 1 (1)
[definitions]
of the
Environmental Management Act
;
order
includes a decision or direction, whether or not the decision or direction is given in writing, but does not include a request;
owner
, in relation to land, a mine or an undertaking in British Columbia, means a person who
a
is entitled to possession of the land, mine or undertaking, or
b
has a substantial interest in the land, mine or undertaking;
permit
means a permit issued under section 24
[permits over Crown land]
or an authority, issued under a former Act, to flood, or to construct, maintain or operate works on, Crown land;
personal information
has the same meaning as in Schedule 1 of the
Freedom of Information and Protection of Privacy Act
;
plan area
means the area designated under section 65
[order designating area for planning process]
for the development of a water sustainability plan;
precedence
, in relation to rights to divert and use water, means the precedence of those rights in accordance with section 22
[precedence of rights]
;
private dwelling
means a structure, or a part of a structure, that is occupied as a private residence;
production casing
, in relation to a well, means the innermost pipe, tubing or other material installed in the well to support the sides of the well, but does not include a well liner or surface casing;
prospecting for a mineral
means searching for a mineral
a
using hand-held tools in a manner that does not involve mechanical disturbance of the surface, or
b
in a prescribed manner;
protected fish population
, in relation to a sensitive stream, means the population of fish in relation to which the stream has been designated as a sensitive stream;
public officer
includes a member of the executive council, a public service employee and any other person, other than a judicial officer, who, under an enactment, has authority to make a decision affecting the rights of another person;
public personal information
means any of the following:
a
the name, address, telephone number and other personal information of a subscriber that appears in a telephone directory, in either printed or electronic form, or is available through a directory assistance service, if
i
the directory or the directory assistance service is available to the public, and
ii
the subscriber is permitted to refuse to have the subscriber's personal information included in the directory or made available by the directory assistance service;
b
personal information that appears in a professional or business directory, listing or notice that is available to the public, if the individual is permitted to refuse to have the individual's personal information included in the directory, listing or notice;
c
personal information appearing in a registry to which the public has lawful access, if the personal information is collected under the authority of an enactment, the laws of the government of Canada or a province of Canada, or the bylaws of a municipality or other similar local authority in Canada;
d
personal information that appears in a printed or electronic publication that is available to the public, including a magazine, book or newspaper in printed or electronic form, unless
i
a court has prohibited the publication or continued publication of the personal information by the source, or
ii
the Information and Privacy Commissioner has made an order stating that the information was published contrary to the
Personal Information Protection Act
;
public service employee
has the same meaning as "employee" in section 1
[definitions]
of the
Public Service Act
;
qualifying agricultural land
means all or the part of a plan area, to which a regulation under section 82 (1)
[plan regulations — dedicated agricultural water]
applies, that is
a
in the agricultural land reserve, or
b
zoned to permit the use of the land for farm use under
i
a municipal or regional district bylaw under Divisions 5 and 12 to 14 of Part 14
[Planning and Land Use Management]
of the
Local Government Act
or Part XXVII
[Planning and Development]
of the
Vancouver Charter
, or
ii
a bylaw made by a local trust committee under section 29
[land use and subdivision regulation]
of the
Islands Trust Act
;
qualifying agricultural use
means the use of water for
a
an irrigation purpose,
b
a prescribed industrial purpose, or
c
a storage purpose associated with a purpose described in paragraph (a) or (b);
recorded water
means water the right to the diversion or use of which is held under an authorization or another enactment;
registrar
, in relation to land, means the registrar appointed under the
Land Title Act
for the land title district in which the land is located;
sensitive stream
means a stream designated by regulation as a sensitive stream;
stream
means
a
a natural watercourse, including a natural glacier course, or a natural body of water, whether or not the stream channel of the stream has been modified, or
b
a natural source of water supply,
including, without limitation, a lake, pond, river, creek, spring, ravine, gulch, wetland or glacier, whether or not usually containing water, including ice, but does not include an aquifer;
stream channel
, in relation to a stream, means the bed of the stream and the banks of the stream, both above and below the natural boundary and whether or not the channel has been modified, and includes side channels of the stream;
take action
,
a
in relation to water, includes allow, start, stop, restrict or prohibit the diversion, use, including storage, carriage or distribution of the water, and
b
in relation to works, includes allow, start, stop, restrict, shut or prohibit their construction or operation;
undertaking
means a project, including all land and other property acquired or to be acquired in connection with the project, and the general scheme for the acquisition, maintenance and operation of the works for the project, for
a
the diversion, carriage, use and sale of water, or
b
the sale of power produced from water,
the water use purpose of which water is referred to in an application or authorization;
unrecorded water
means water in a stream or an aquifer that is not recorded water;
use approval
means an approval issued under section 10
[use approvals]
or written approval, other than a licence, to divert and use water, given under a former Act;
water district
means a water district prescribed by regulation;
water manager
means a person designated under section 114 (3)
[administration]
as a water manager;
water objective
means an objective established by regulation under section 43
[water objectives]
;
water source well
has the same meaning as in section 1
[definitions]
of the
Petroleum and Natural Gas Act
;
water sustainability plan
means a water sustainability plan accepted under section 75 (1) or (3)
[acceptance of plan]
;
water use purpose
means a purpose defined in section 2
[water use purposes]
or a subset of a purpose defined in section 2;
water users' community
has the same meaning as in section 1 (1)
[definitions]
of the
Water Users' Communities Act
;
well
means an artificial opening in the ground made for the purpose of
a
exploring for or diverting groundwater,
b
testing or measuring groundwater,
c
recharging or dewatering an aquifer,
d
groundwater remediation,
e
use as a monitoring well,
f
use as a closed-loop geoexchange well, or
g
use as a geotechnical well,
but does not include
h
an artificial opening, other than a water source well, to which the
Geothermal Resources Act
or the
Energy Resource Activities Act
applies, or
i
an artificial opening of a prescribed class, made for a prescribed purpose or in prescribed circumstances;
well cap
means a secure cap or lid that prevents vermin, contaminants, debris or other foreign objects or substances from entering the interior of the production casing, and includes a sanitary well seal;
well cover
means a secure cover, lid or structure that prevents vermin, contaminants, debris or other foreign objects or substances from entering the well;
well pump
means a pump that
a
is at or in a well, and
b
is used or intended to be used for the purposes of
i
diverting groundwater from a well,
ii
adding water to a well to recharge the well or an aquifer, or
iii
dewatering an aquifer;
wellhead
means
a
the physical structure, facility, well cover, adapter or device
i
that is at the top of, or at the side and near the top of, a well, and
ii
from or through which groundwater flows or is pumped from the well, and
b
any casing, well cap, valve, grout, liner, seal, vent or drain relating to the well,
but does not include a well pump or a pump house;
wetland
means a swamp, marsh, fen or prescribed feature;
wildlife
means wildlife as defined in paragraph (a) of the definition of "wildlife" in section 1 (1)
[definitions and interpretation]
of the
Wildlife Act
;
works
means
a
anything that can be or is used for
i
diverting, storing, measuring, conserving, conveying, retarding the flow of, confining or using water,
ii
producing, measuring, transmitting or using electricity,
iii
collecting, conveying or disposing of sewage or garbage, or
iv
preventing or extinguishing fires,
b
booms and piles placed in a stream,
c
obstructions placed in or removed from streams or the banks or beds of streams,
d
changes in and about a stream,
e
access roads to any of the works referred to in paragraphs (a) to (d) or (f) (i), and
f
wells and works related to wells, including
i
wellheads,
ii
anything that can be or is used for injecting or otherwise adding water or any other substance to a well,
iii
anything that can be or is used for constructing, deactivating or decommissioning a well,
iv
anything that can be or is used for exploring for, testing, diverting or monitoring groundwater,
v
anything that can be or is used for disinfecting a well,
vi
an injection system attached to a work that is used for conveying, from a well, groundwater that will be used for applying fertilizers or pesticides, and
vii
anything that can be or is used in relation to a monitoring well or a well made for the purpose of groundwater remediation.
2
A reference in this Act to regulations or to anything as prescribed is a reference to regulations of the Lieutenant Governor in Council unless specifically provided otherwise in the applicable provision.
3
An authorization, change approval, permit or drilling authorization issued in substitution for
a
an original authorization, change approval, permit or drilling authorization, or
b
an original authorization, change approval, permit or drilling authorization as modified,
is conclusively deemed to be the original authorization, change approval, permit or drilling authorization as modified.
4
A reference in this Act
a
to an aquifer includes part of an aquifer, and
b
to a stream includes part of a stream.
Water use purposes
2
The following defined purposes are the purposes in respect of which water may be diverted from a stream or an aquifer:
conservation purpose
means the diversion, retention or use of water for the purpose of conserving fish or wildlife and includes the construction of works for that purpose;
domestic purpose
means the use of water for household purposes by the occupants of, subject to the regulations, one or more private dwellings, other than multi-family apartment buildings, including, without limitation, hotels and strata titled or cooperative buildings, located on a single parcel, including, without limitation, the following uses:
a
drinking water, food preparation and sanitation;
b
fire prevention;
c
providing water to animals or poultry kept
i
for household use, or
ii
as pets;
d
irrigation of a garden not exceeding 1 000 m
2
that is adjoining and occupied with a dwelling;
industrial purpose
means a use of water designated by regulation as a use for an industrial purpose, but does not include the use of water for any other water use purpose;
irrigation purpose
means the use of water on cultivated land or hay meadows to nourish crops or on pasture to nourish forage;
land improvement purpose
means the diversion or impounding of water to
a
protect land,
b
facilitate the development of a recreational facility or of a park or other protected area,
c
facilitate the reclamation, drainage or other improvement of land, or
d
carry out a project of a nature similar to a project described in paragraph (b) or (c);
mineralized water purpose
means
a
the bottling and commercial distribution of water so impregnated with mineral salts, elements or gases as to potentially give the water therapeutic properties, or
b
the use in commercial bathing pools of water that is
i
impregnated with mineral salts, elements or gases, or
ii
naturally at a temperature suitable for that use;
mining purpose
means
a
the use of water, including the use of water under pressure, for recovering minerals from the ground or from ore, or
b
the use of water under pressure to move earth, sand, gravel or rock;
oil and gas purpose
means the use of water in the development of petroleum or natural gas wells or the production of petroleum or natural gas resources;
power purpose
means the use of water in the production of electricity or other power;
storage purpose
means the impounding and retention of water for subsequent use for a water use purpose;
waterworks purpose
means the carriage or supply of water by one person or entity for the use in British Columbia of another person or entity.
Water Protection Act
3
Nothing in this Act authorizes a person to do anything prohibited by the
Water Protection Act
.
Geothermal resources
4
This Act does not apply to geothermal resources as defined in section 1 (1)
[definitions]
of the
Geothermal Resources Act
.
Vesting water in government
5
1
The property in and the right to the use and flow of all the water at any time in a stream in British Columbia are for all purposes vested in the government, except insofar as private rights have been established under authorizations.
2
The property in and the right to the use, percolation and flow of groundwater, wherever groundwater is found in British Columbia, are for all purposes vested in the government and are conclusively deemed to have always been vested in the government except insofar as private rights have been
a
established under authorizations, or
b
deemed under section 22 (8)
[precedence of rights]
.
3
No right to divert or use water may be acquired by prescription.
Use of water
6
1
Subject to this section, a person must not divert water from a stream or an aquifer, or use water diverted from a stream or an aquifer by the person, unless
a
the person holds an authorization authorizing the diversion or use, or
b
the diversion or use is authorized under the regulations.
2
A person is not prohibited from
a
diverting or storing and beneficially using water from a stream or an aquifer for extinguishing a fire, but if flow is diverted from a stream channel for that use, the flow must promptly be restored to that stream channel when the fire is extinguished, or
b
diverting water to test the quality or quantity of water or to conduct a flow test.
3
Unless regulations under section 135 (5)
[regulations closing or restricting access to water source]
provide otherwise, a person is not prohibited from diverting, in accordance with any applicable regulations, and beneficially using unrecorded water
a
from a stream for domestic purpose or for prospecting for a mineral, or
b
from an aquifer for prospecting for a mineral.
4
A person may, in accordance with the regulations, divert, and beneficially use, including store, groundwater from an aquifer for domestic purpose unless
a
provided otherwise by regulations under section 135 (6), or
b
this subsection does not apply to the applicable aquifer by regulations under section 136
[regulations requiring authorizations for domestic use of groundwater]
.
Rights acquired under authorizations
7
1
A licence entitles its holder to do the following in a manner provided in the licence:
a
divert and beneficially use the quantity of water specified in the licence;
b
construct, maintain and operate the works authorized by the licence and related works necessarily required for the proper diversion or use of the water or the power produced from the water;
c
make changes in and about a stream necessary for the construction, maintenance or operation of the works referred to in paragraph (b) or to otherwise facilitate the authorized diversion;
d
construct fences, screens and fish or game guards across streams for the purpose of conserving fish or wildlife.
2
A use approval entitles its holder to do anything described in subsection (1) for the period or at the times and in the manner specified in the use approval.
Rights and permissions subject to Act
8
1
The exercise of a right held under an authorization is subject to this Act and the regulations, the terms and conditions of the authorization, the orders of the comptroller, a water manager or an engineer and the rights of all authorization holders whose rights have precedence.
2
The exercise of permission given under a change approval is subject to this Act and the regulations, the terms and conditions of the change approval, the orders of the comptroller, a water manager or an engineer, the rights of authorization holders and the rights of holders of change approvals issued before the date of the change approval.
3
The exercise of permission given under a permit is subject to this Act and the regulations, the terms and conditions of the permit and the orders of the comptroller, a water manager or an engineer.
4
The exercise of permission given under a drilling authorization is subject to this Act and the regulations, the terms and conditions of the drilling authorization and the orders of the comptroller, a water manager or an engineer.
Licences
9
On application in accordance with section 12
[application and decision maker initiative procedures]
, the comptroller or a water manager may issue a licence, authorizing the diversion or use of water for one or more water use purposes, to any of the following:
a
an owner of land or a mine;
b
a holder of a certificate of public convenience and necessity issued under the
Public Utilities Act
, R.S.B.C. 1960, c. 323, the
Utilities Commission Act
or the
Water Utility Act
;
c
a municipality, regional district, improvement district, development district or water users' community;
d
the government of British Columbia or Canada;
e
a commission, board or person having charge of the administration of Crown land or a mine or an undertaking on Crown land, administered by British Columbia or Canada or controlled by a ministry, department, branch or other subdivision of the government of British Columbia or Canada;
f
the Greater Vancouver Water District or any other water district incorporated by an Act;
g
the British Columbia Hydro and Power Authority.
Use approvals
10
1
On application in accordance with section 12
[application and decision maker initiative procedures]
, the comptroller or a water manager may issue an approval for one or more water use purposes authorizing any of the following to divert or use water from a stream or an aquifer for a term not exceeding 24 months:
a
the government of British Columbia or Canada;
b
another person.
2
A use approval under this section must not authorize
a
the diversion or use of more than the prescribed quantity of water,
b
the diversion or use of water for a prescribed water use purpose, or
c
the construction, maintenance or use of prescribed works.
3
For certainty, a use approval may be issued authorizing a person to divert water from a source of water supply for a water use purpose in relation to an appurtenancy, if any, specified in the use approval, whether or not a use approval was previously issued authorizing the person to divert water from the same water source supply for the same water use purpose in relation to the same appurtenancy.
Changes in and about a stream
11
1
On application in accordance with section 12, the comptroller, a water manager or an engineer may issue an approval authorizing any of the following persons to make changes in and about a stream:
a
the government of British Columbia or Canada;
b
another person.
2
Changes in and about a stream may only be made in accordance with
a
the terms and conditions of a change approval,
b
the regulations,
c
the terms and conditions of an authorization, or
d
an order.
Application and decision maker initiative procedures
12
1
An applicant may apply to a decision maker by
a
complying with any requirements prescribed in respect of the application, and
b
within the period, if any, prescribed by regulation,
i
complying with the decision maker's directions under section 13 (1) or (9), if any,
ii
paying the prescribed fees,
iii
providing in the form and manner specified by the decision maker any plans, specifications, reports of assessments and other information the decision maker requests, which information may include, but is not limited to, public personal information that is relevant to the application, respecting
A
the applicant,
B
existing water users, riparian owners, other applicants and other authorization holders, whose rights are likely to be detrimentally affected if the application is granted, and
C
land owners whose land is likely to be physically affected if the application is granted, and
iv
providing in the form and manner specified by the decision maker the consents that are necessary for the decision maker to verify personal information relating to the applicant that is provided under subparagraph (iii).
2
For the purposes of subsection (1) (b) (iii), the decision maker may require that a specified assessment be performed, and a report of the assessment be prepared, by a person with the qualifications specified by the decision maker.
3
For the purpose of making a decision on an application, the decision maker may
a
collect contact information from the applicant, and collect public personal information and government water records, related to a person referred to in subsection (1) (b) (iii), and
b
verify information collected under this subsection or provided under subsection (1) or (2), including, in relation to
i
personal information of the applicant, by consent or by reference to public personal information or government water records, and
ii
personal information of a person referred to in subsection (1) (b) (iii) (B) or (C), by direct contact with the person or by reference to public personal information or government water records.
4
If works are required to be constructed in order for the applicant to obtain information required for the purposes of subsection (1) (b) (iii), the applicant may construct, in accordance with any applicable regulations, the works for that purpose, subject to any applicable requirement for a drilling authorization in relation to the works.
5
The decision maker may
a
shorten or extend the period prescribed for the purposes of subsection (1) (b), or
b
if no period has been prescribed, set a period for compliance with a direction or request, if any, referred to in subsection (1) (b).
6
A decision maker may exercise the powers under this section in relation to an initiative of the decision maker under section 21
[when final licence may be issued]
, 26
[amendment or substitution of authorization, change approval or permit]
, 28
[apportionment of rights under licences]
or 62
[drilling authorizations]
.
Objections to applications and decision maker initiatives
13
1
A decision maker must direct that an applicant for a licence, use approval or change approval, or for an amendment to any of them involving a change of works, give notice of the application in accordance with section 117
[delivery and publication of documents and information]
or the regulations to
a
any of the following whose rights the decision maker considers are likely to be detrimentally affected if the application is granted:
i
an authorization holder;
ii
a change approval holder;
iii
an applicant for an authorization or change approval;
iv
a riparian owner, and
b
a land owner whose land is likely to be physically affected if the application is granted.
2
A notice under subsection (1) must include the name of the decision maker and the address to which objections to the application may be delivered.
3
A person who is given notice under subsection (1) may deliver to the decision maker identified in the notice within the prescribed period any objection the person has to the granting of the application.
4
If an objection is delivered in accordance with subsection (3), the decision maker must decide whether or not the objection warrants a hearing.
5
If the decision maker decides to hold a hearing, the decision maker must
a
give notice to the applicant and to any person who delivered an objection under subsection (3) of
i
the date, time and location of the hearing, or
ii
the date by which written submissions must be received by the decision maker, and
b
give the applicant and the objectors the opportunity to be heard in the hearing.
6
The decision maker may hold a hearing in writing, electronically or in person or by any combination of written, electronic or in-person hearings and, if the hearing is held orally, either in person or electronically, sections 95
[inquiry powers]
, 96
[maintenance of order at hearings]
and 97
[contempt proceeding for uncooperative person]
apply.
7
The decision maker must give notice of the decision maker's decision on an application to any person who delivered under subsection (3) an objection in relation to the application.
8
For certainty, a decision maker need not give directions under subsection (1) if the decision maker is satisfied that, as a result of the decision maker's decision on an application referred to in that subsection,
a
no authorization holder's rights, no change approval holder's rights and no riparian owner's rights will be detrimentally affected,
b
no person's land will be physically affected, and
c
no person's application for an authorization or a change approval will be detrimentally affected.
9
A decision maker may direct that any applicant, and in the case of a transfer under section 27
[transfer of appurtenancy]
, the transferee, give notice in accordance with section 117 or the regulations,
a
in the case of an apportionment under section 28
[apportionment of rights under licences]
, to the owner of each parcel affected by the apportionment,
b
in the case of an abandonment of rights under section 31
[abandonment of rights under an authorization]
, to anyone who is jointly using works with the applicant and any person whose land is physically affected by the existing works, and
c
in any case, to any person whose input into the decision the decision maker considers advisable.
10
Subsections (2) to (7) apply if notice is given under subsection (9) (a) or (b).
11
Despite subsection (10), if a decision maker gives, or requires to be given, notice under subsection (9), the decision maker may specify how, and the date by which, a person given notice may object to the application.
12
A person given notice under subsection (9) (c) is not entitled to be heard in a hearing under this section.
13
If a decision maker initiates the issuance of a final licence under section 21
[when final licence may be issued]
, a 30-year review under section 23, an amendment under section 26
[amendment or substitution of authorization, change approval or permit]
or an apportionment under section 28, subsections (9) to (12) of this section apply unless the amendment requires a change of works, in which case subsections (1) to (8) and (14) of this section apply.
14
Instead of requiring the applicant or a transferee to give a notice required under subsection (1) or (9), the decision maker may give the notice.
Powers respecting applications and decision maker initiatives
14
1
Whether or not notice is given, or objections are delivered, under section 13 in relation to an application, the decision maker may, in accordance with this Act and the regulations,
a
refuse the application,
b
amend the application in any respect,
c
grant all or part of the application,
d
order the applicant to provide in the form and manner specified by the decision maker plans, specifications, reports of assessments or other information, which information may include, but is not limited to, public personal information that is relevant to the application, respecting
i
the applicant,
ii
existing water users, riparian owners, other applicants and other authorization holders, whose rights are likely to be detrimentally affected if the application is granted, and
iii
land owners whose land is likely to be physically affected if the application is granted,
e
order the applicant to provide security to the decision maker in the amount the decision maker considers sufficient to ensure the performance of the applicant's obligations under this Act and the authorization, change approval or drilling authorization, as applicable, that is issued to the applicant, or
f
issue to the applicant, subject to prescribed terms and conditions and on the terms and conditions the decision maker considers advisable,
i
one or more conditional licences or final licences, or
ii
a use approval, a change approval or a drilling authorization, as applicable.
2
An applicant must comply with an order made under subsection (1) (d) or (e) within the period specified by the decision maker.
3
For the purposes of subsection (1) (d), the decision maker may require that a specified assessment be performed, and a report of the assessment be prepared, by a person with the qualifications specified by the decision maker.
4
If an application is for the purpose of diverting water from an aquifer, the decision maker must take into account the quantity of water persons to whom section 6 (4)
[use of water — excluded groundwater users]
applies are authorized to divert from the aquifer.
5
In considering an application for a new licence that relates to the region as defined by the
Columbia Basin Trust Act
, the decision maker must consider the current long term Columbia Basin Management Plan under section 15
[Columbia Basin Management Plan]
of that Act.
6
Without limiting subsection (1), the decision maker may refuse an application, or reject an application without considering it, if
a
the applicant fails to comply with
i
section 12 (1)
[application and decision maker initiative procedures]
,
ii
a direction under section 13 (1) or (9),
iii
an order under subsection (1) (d) or (e) of this section, or
iv
an order or a direction referred to in this paragraph within the required period,
b
in the case of an application for a use approval or change approval, the decision maker considers the proposed use of water or the proposed works would be more properly authorized by licence, or
c
the application is incomplete.
7
A decision maker must refuse to accept an application or a part of an application that would result in the issuance of an authorization to a person to whom section 6 (4)
[use of water — excluded groundwater users]
applies.
8
A decision maker may not issue a licence authorizing the diversion or use of dedicated agricultural water unless the licence is for a qualifying agricultural use on qualifying agricultural land.
9
Despite subsection (8), a licence may be issued authorizing the diversion or use of unrecorded dedicated agricultural water for domestic purpose or a land improvement purpose.
10
A decision maker may exercise the powers under this section in relation to an initiative of the decision maker under section 21
[when final licence may be issued]
, 26
[amendment or substitution of authorization, change approval or permit]
, 28
[apportionment of rights under licences]
or 62
[drilling authorizations]
.
11
For certainty, a use approval may be issued authorizing the diversion or use of unrecorded dedicated agricultural water for any water use purpose on any land.
Environmental flow needs
15
1
Except in relation to an application exempted under the regulations, the decision maker must consider the environmental flow needs of a stream in deciding an application in relation to the stream or an aquifer the decision maker considers is reasonably likely to be hydraulically connected to that stream.
2
For an application in respect of which the decision maker must consider, or decides under subsection (4) to consider, the environmental flow needs of a stream,
a
the applicant must provide to the decision maker the information and reports of assessments the decision maker directs for the purposes of paragraph (b) of this subsection, and
b
the decision maker must determine, in accordance with any applicable regulations, the environmental flow needs of the applicable stream.
3
For the purposes of subsection (2) (a), the decision maker may require that a specified assessment be performed, and a report of the assessment be prepared, by a person with the qualifications specified by the decision maker.
4
Despite subsection (1), a decision maker may take into account the environmental flow needs of any stream the decision maker considers may be affected by granting the application.
Mitigation measures
16
1
If the decision maker considers that the diversion and use of water, or changes in and about a stream, proposed by an application for an authorization, or the changes in and about a stream proposed to be made under a change approval, are likely to have a significant adverse impact on the water quality, water quantity or aquatic ecosystem of a stream or aquifer, a stream channel or other uses of water from the stream or aquifer to which the application relates, the decision maker may
a
require that the applicant submit a proposal for mitigation measures to address those effects, which mitigation measures must meet prescribed criteria, if any, and
b
impose under section 14 (1) (f)
[powers respecting applications and decision maker initiatives]
terms and conditions requiring implementation of the proposed mitigation measures if those measures meet the prescribed criteria.
2
If the decision maker considers that the effects described in subsection (1) cannot be addressed, or cannot be fully addressed, by mitigation measures proposed by the applicant but can be compensated for by other mitigation measures taken on a different part of the stream or aquifer than the part to which the proposal relates, the decision maker may impose under section 14 (1) (f) terms and conditions requiring the applicant to take compensatory mitigation measures that meet the prescribed criteria, in place of or supplemental to any mitigation measures proposed by the applicant, on a different part of the stream or aquifer to which the application relates.
3
With the consent of the applicant, the terms and conditions of an authorization or change approval may require that the applicant take compensatory mitigation measures on a different stream or aquifer than the stream or aquifer in respect of which the application is made.
Sensitive streams mitigation
17
1
If an application for an authorization or a change approval, or an amendment to an authorization or change approval, is in relation to a sensitive stream, the decision maker
a
may require that the applicant provide the prescribed plans, specifications, reports of assessments or other information, in addition to the other information required under this Act in relation to the application, and
b
must apply prescribed criteria, if any, in addition to the other criteria to be applied under this Act, in deciding whether to grant the application.
2
An application described in subsection (1) must include mitigation measures that meet the prescribed criteria, if any, and that the applicant proposes to take to mitigate any adverse impact on a protected fish population resulting from granting the application in relation to the sensitive stream.
3
The decision maker may grant an application described in subsection (1) only
a
if satisfied that
i
any adverse impact, resulting from granting the application, on the sustainability of any protected fish population of the sensitive stream is likely to be insignificant,
ii
the mitigation measures proposed by the applicant, if carried out, would ensure that granting the application is not likely to cause a significant adverse impact on any protected fish population or the aquatic ecosystem of the sensitive stream, or
iii
compensatory mitigation measures that meet any prescribed criteria, whether or not proposed by the applicant, if carried out, in place of or supplemental to the proposed mitigation measures, will enhance or enable the enhancement of an aquatic ecosystem elsewhere that will fully compensate for the significant adverse impact on that protected fish population or aquatic ecosystem resulting from granting the application, and
b
if, in the circumstances described in paragraph (a) (ii), the decision maker imposes implementation of the mitigation measures, and in the circumstances described in paragraph (a) (iii), the decision maker imposes implementation of the compensatory mitigation measures, as terms and conditions of the authorization or change approval or amended authorization or change approval, as applicable.
4
If the decision maker considers that there is a reasonable alternative source of water reasonably available to an applicant making an application referred to in subsection (1), the decision maker may refuse to grant the application.
Not in force
18
[Not in force.]
Licences for power purposes
19
1
In this section:
operational term
means the period beginning when
a
the activities described in the definition of "project development term" are completed, or
b
the period authorized for completion of those activities has ended,
whichever occurs earlier, during which power is, or is authorized to be, produced under a licence issued for a power purpose and during which a storage purpose authorized by a licence in relation to the power purpose may be exercised;
project development term
means the period, following the issue of a licence for a power purpose but before the beginning of the operational term, during which activities required to prepare for power production under the licence are performed, including, without limitation, project design and engineering, securing construction and other contracts and constructing works.
2
This section applies to
a
a licence issued for a power purpose on or after October 23, 2003, unless the licence is being issued in substitution for a licence that did not specify the term of the licence and was issued for a power purpose before that date,
b
a licence that is being amended, whether or not the licence is replaced, if
i
the licence was issued for a power purpose before October 23, 2003 and specified the term of licence, and
ii
the amendment is for the purpose of extending the term of the licence, or
c
a licence that is being amended, whether or not the licence is replaced, if
i
the licence was issued for a purpose other than a power purpose, and
ii
the amendment is for the purpose of authorizing the use of water for a power purpose.
3
The decision maker must not issue a licence to which this section applies that has an operational term longer than 40 years.
4
The decision maker may provide in a licence described in subsection (2) (a) or (c) for a project development term of up to 10 years.
5
The holder of a licence issued to authorize the use of water for a power purpose may apply to renew the licence before the expiry of the operational term of that licence.
6
Despite section 26
[amendment or substitution of authorization, change approval or permit]
, this Act and the regulations apply to the following applications as if the application were for a new licence:
a
an application for an amendment referred to in subsection (2) (b) (ii);
b
an application for an amendment referred to in subsection (2) (c) (ii);
c
an application to extend the term of a licence to which this section applies.
7
The rights exercisable under a licence to which this section applies that is issued in substitution for or as a renewal of another licence have precedence from the same date as the rights under the licence that is replaced.
8
Despite subsection (3), if an application is made under subsection (5), the licence does not expire until the later of
a
the date the decision maker decides on the application, and
b
the expiry date of the operational term of the licence.
9
If a licensee fails to apply to renew a licence to which this section applies before the expiry of the operational term of the licence and the failure, in the opinion of the decision maker, is not the fault of the licensee, the decision maker may extend the expiry date for not more than 6 months from the original expiry date and, if the expiry date is extended, the licence is deemed to be and to have been continuously in force from the date of issue until the new expiry date.
10
Subsection (9) does not apply to a licence for which the expiry date has been extended under that subsection.
11
A decision under subsection (9) of this section to refuse to extend an expiry date is final and may not be appealed to the appeal board.
Purpose, precedence and appurtenancy
20
1
A decision maker must ensure that a licence that the decision maker issues specifies as the appurtenancy of the licence an appurtenancy
a
that, except in relation to a licence that is required to be registered under the
Water Protection Act
, is located entirely in British Columbia,
b
that consists of land, a mine or an undertaking, or any combination of those things, and
c
that is adequately described in the licence.
2
A decision maker who issues a use approval, change approval, permit or drilling authorization may specify an appurtenancy that meets the requirements of subsection (1) as the appurtenancy of the use approval, change approval, permit or drilling authorization, as applicable.
3
The decision maker must ensure that every authorization that the decision maker issues
a
specifies the date of precedence of the rights under the authorization,
b
specifies the maximum quantity of water that may be diverted and used for each water use purpose authorized by the authorization, and
c
is for the diversion of water for one or more water use purposes and those water use purposes are specified in the authorization.
When final licence may be issued
21
1
On application under section 12
[application and decision maker initiative procedures]
, or on the comptroller's or water manager's own initiative, the comptroller or a water manager may issue to the holder of a conditional licence a final licence authorizing the diversion or use of the quantity of water that the decision maker determines to have been beneficially used for the water uses purposes authorized under, and during the term of, the conditional licence, when
a
the licensee completes the works, or
b
the period for completing the works expires and, if any works have not been completed, the decision maker determines that the works that have not been completed are not required.
2
On the issue of a final licence, the conditional licence it replaces has no further effect.
Precedence of rights
22
1
The rights exercisable under an authorization that authorizes the diversion of water from a stream have precedence in relation to the rights of other authorization holders who divert water from
a
the stream,
b
a tributary of the stream, or
c
an aquifer the decision maker considers is reasonably likely to be hydraulically connected to that stream
according to the dates set out in the authorizations as the dates from which the rights take precedence.
2
The rights exercisable under authorizations described in subsection (1) that have precedence from the same date have precedence in accordance with the ranking under subsection (7) of the water use purposes in respect of which the authorizations are issued.
3
The rights exercisable under authorizations described in subsection (1) have equal precedence if the rights have precedence from the same date and are for the same water use purpose.
4
The rights exercisable under an authorization that authorizes the diversion of water from an aquifer have precedence in relation to the rights of other authorization holders who divert water from the aquifer, or another aquifer the decision maker considers is reasonably likely to be hydraulically connected to that aquifer, according to the date set out in the authorization as the date from which the rights take precedence.
5
The rights exercisable under authorizations described in subsection (4) that have precedence from the same date have precedence in accordance with the ranking under subsection (7) of the water use purposes in respect of which the authorizations are issued.
6
The rights exercisable under authorizations described in subsection (4) have equal precedence if the rights have precedence from the same date and are for the same water use purpose.
7
For the purposes of subsections (2) and (5), water use purposes are ranked, from highest to lowest as follows:
a
domestic;
b
waterworks;
c
irrigation;
d
mineralized water;
e
mining;
f
industrial;
g
oil and gas;
h
power;
i
storage;
j
conservation;
k
land improvement.
8
Despite subsections (1) to (6), a person to whom section 6 (4)
[use of water — excluded groundwater users]
applies is deemed to have rights that have precedence under those subsections, as if the deemed rights were granted under an authorization that
a
sets out as the date of precedence the date of first use of the water, and
b
authorizes the use of the greater of
i
2 000 litres of water per day for each private dwelling on a parcel, or
ii
the amount of water the engineer is satisfied the person has been using for domestic purposes.
9
Despite subsections (1) to (8), if an order under section 86 (1) or (3)
[declarations of significant water shortage]
applies to a stream and the comptroller has determined the critical environmental flow threshold for the stream under section 87 (1)
[critical environmental flow protection orders]
, the amount of that critical environmental flow threshold for the stream has precedence over the rights
a
under any authorization issued in relation to the stream or a hydraulically connected aquifer referred to in subsection (1) of this section, or
b
of a person described in subsection (8) of this section.
10
Despite subsections (1) to (9), if an engineer is taking action to enforce the precedence of rights to divert or use water from a stream or aquifer, a person must not be prohibited from diverting water from the stream or aquifer for essential household use.
11
For the purposes of this section,
essential household use
means the use by the occupants of one private dwelling of not more than 250 litres of water per day for
a
drinking water, food preparation and sanitation, and
b
providing water to animals or poultry that are kept
i
for household use, or
ii
as pets.
Thirty-year review of licence terms and conditions
23
1
This section applies to a licence that
a
was issued on or before the date this section comes into force for an unlimited period or that has, at that date, at least 30 years remaining in its term, or
b
is issued after the date this section comes into force for an unlimited period or a term exceeding 30 years,
but does not apply to licences
c
issued for a power purpose, or a storage purpose related to a power purpose, on or after October 23, 2003,
d
issued under the
Industrial Development Act
, or
e
issued following a review, or reviewed, under the Water Use Plan directives published by the government and dated December 1998.
2
On the direction in writing of the comptroller or a water manager, a licensee who holds a licence to which this section applies must submit to a review of the terms and conditions of the licence,
a
for a licence issued on or before the date this section comes into force, any time that is at least 30 years after that date, and any time that is at least 30 years after the immediately preceding review under this section, and
b
for a licence issued after the date this section comes into force, any time after the licence has been in effect for 30 years after its issue and any time that is at least 30 years after the immediately preceding review under this section.
3
A licensee who is given a direction under subsection (2) must, within the period specified in the direction, provide to the decision maker who gave the direction,
a
the information, plans, specifications and reports of assessments, including a water conservation audit carried out in accordance with and meeting the requirements of the regulations, specified by the decision maker, and
b
in the form and manner specified by the decision maker, the consents that are necessary for the decision maker to verify information provided under paragraph (a).
4
The decision maker may require that a specified assessment be performed, and a report of the assessment be prepared, by a person with the qualifications specified by the decision maker.
5
Section 12 (1) (b) (iii), (2) and (3) applies for the purpose of a review under this section.
6
The decision maker may review the terms and conditions of a licence taking into account
a
the best available technology in respect of water use efficiency and water conservation,
b
best practices in respect of water use efficiency and water conservation,
c
any increase in knowledge respecting actual stream flow or aquifer conditions,
d
the effects of climate change,
e
the licensee's beneficial use of the water,
f
the use, operation or maintenance of works, and
g
prescribed factors.
7
On a review under this section, the decision maker may amend the terms and conditions of the licence to require the licensee, for the more efficient use or conservation of water, to
a
reduce the maximum rate of diversion of water under the licence,
b
alter the time of diversion or use, including storage, of water under the licence,
c
construct, alter, install, replace, repair, maintain, improve, seal, deactivate, decommission or remove any works, or
d
adopt a more efficient practice.
8
If the decision maker considers that the changes under this section in terms and conditions of a licence would sub
The text continues in the official source.
Contains information licensed under the King’s Printer Licence for British Columbia. This reproduction is not an official copy.